Which drywall finish level requires no taping or finishing?

  1. Level 0

  2. Level 1

  3. Level 2

  4. Level 5

The correct answer is: Level 0

Level 0 drywall finish is defined as a stage where there is no taping or finishing applied to the drywall. This level is typically used in temporary construction situations or where the drywall will be covered by another material. It establishes a baseline where the drywall is simply installed but not treated in any way to create a smooth or visually appealing surface. In contrast, other levels of drywall finishing include various stages of taping, filling, and sanding to smooth out joints and seams. Level 1 includes taping the joints but does not require finishing, while Level 2 typically requires a coat of joint compound over taped joints. Level 5 involves the highest degree of finishing, including a full coat of joint compound to avoid imperfections showing through paint. Thus, level 0 is unique in that it requires no additional work beyond the installation of the drywall itself.